Power Measurement, with Traffic control by LabVIEW

Power Measurement, with Traffic control by LabVIEW

Power Measurement, with Traffic control by LabVIEW

  • The UUT is being powered-up by the EEC 6650 Power Source for 3min using @ UUT setting of High Heat and High Flow ( max settings).

  • A power meter is also used to monitor the power consumption of the UUT during this time.

  • If the UUT passed the required power levers (depends on UUT), the UUT will be marked as Good, otherwise FAIL. The Power (V,I,P) reading will be data logged either pass or fail to PC.


 